Myanmar - Ridge Gourd
Activity | Activity item | Average Cost | No. of times used |
---|---|---|---|
Land Preparation | Lime | 3,951.1 Kyats (K 1000) /500sqm | 29 times |
Land Preparation | Bed preparation | 3,664.2 Kyats (K 1000) /500sqm | 22 times |
Land Preparation | Ploughing | 1,723.5 Kyats (K 1000) /500sqm | 18 times |
Land Preparation | Labor hired | 1,146.3 Kyats (K 1000) /500sqm | 6 times |
Land Preparation | Manure | 738.1 Kyats (K 1000) /500sqm | 7 times |
Land Preparation | Clearing | 186.1 Kyats (K 1000) /500sqm | 3 times |
Total | 11,409.3 Kyats (K 1000) /500sqm |